For years, solar has largely been viewed as a value-add: a tool to reduce operating costs, strengthen project economics, and improve sustainability metrics. Under New York’s 2025 Energy Conservation Construction Code (ECCCNYS), however, renewable energy has become something more: a code compliance consideration.

Yet many developers are still unaware of one of the code’s most consequential changes.

Section C405.15 of the 2025 ECCCNYS, which went into effect December 31, 2025, requires new commercial buildings over 5,000 square feet to incorporate renewable energy, either through on-site generation or, under qualifying circumstances, off-site renewable energy procurement.

The result? Decisions about commercial solar can no longer wait until the end of the design process.

Whether you’re developing affordable housing, a new warehouse or manufacturing facility, a municipal building, or a commercial office, here are five questions worth asking before the first set of plans is finalized.

a new commercial building with a rooftop solar array with overlaid copy that reads "New York's Energy Code Solar Requirements"

1. Does my project trigger New York's renewable energy requirements?

The first question is also the most important.

Under Section C405.15.1, new buildings are generally required to provide on-site renewable energy generation equivalent to 0.75 watts per square foot of conditioned floor area, subject to the code’s calculation methodology. Buildings smaller than 5,000 square feet are exempt.

Many project teams assume solar is optional unless required by an owner, lender, utility program, or sustainability goal. The 2025 code changes that conversation.

For many new construction projects, renewable energy is no longer solely an economic or environmental decision. It is a compliance issue.

The New Solar Energy Code Requirement

Buildings > 5,000 square feet must add .75 watts of on-site renewable energy generation per sq. ft. of conditioned floor area

2. Have we allocated enough usable roof space?

One of the biggest risks is not the cost of solar itself. It’s designing a building without solar in mind that leaves few practical options for compliance.

As projects advance, rooftops often become crowded with mechanical equipment, access pathways, occupied roof terraces, green roof features, and other infrastructure. By the time solar enters the discussion, the available space may be significantly reduced.

The code recognizes these constraints. Buildings with more than 80% of the roof occupied by permanent obstructions may qualify for an alternative compliance pathway, under C405.15.2.

But relying on exemptions after design is rarely as efficient as evaluating renewable energy requirements during conceptual planning. Even for projects that do not intend to install solar immediately, preserving solar-ready roof space can create long-term flexibility.

 

Rooftop designed without solar in mind

As energy costs, tenant expectations, and building performance requirements continue to evolve, solar-friendly design decisions made during planning can help avoid costly retrofits later.

For architects and engineers, roof planning is no longer just an architectural exercise. It is now an energy code exercise as well.

3. If we can't install solar, what is our compliance strategy?

One of the biggest misconceptions surrounding the code is that projects can simply opt out of solar if they don’t want it.

That is not how Section C405.15 is structured.

Projects that qualify for certain exceptions, including buildings with significant roof obstructions or shading limitations, transition to Section C405.15.2, which requires procurement of off-site renewable energy, such as a community solar contract.

In other words, the code does not simply ask whether a project can install solar. It asks how the project will satisfy its renewable energy obligation.

For some projects, rooftop solar will remain the simplest path. For others, off-site renewable procurement may become the more practical solution.

What if you can’t install rooftop solar?

Buildings that qualify for an exception must procure an off-site renewable energy contract, such as community solar.

4. Are we starting early enough?

Perhaps the biggest mistake project teams can make is assuming renewable energy compliance can be addressed later.

By the time construction documents are nearing completion, many of the decisions that impact compliance have already been made. Roof space may be fully allocated. Structural assumptions may be finalized. Electrical systems may already be designed around a specific project scope. At that stage, adding renewable energy can become more complicated, more expensive, and more restrictive than it would have been during schematic design.

That’s why timing matters.

Whether a project ultimately pursues on-site solar, qualifies for an exception, or utilizes an off-site renewable energy pathway, evaluating those options early gives project teams greater flexibility and a wider range of solutions.

The goal is not simply to avoid compliance issues. It’s to make informed design decisions before those decisions become difficult or costly to change.

5. Are we involving the right partners?

Historically, many developers evaluated solar after site plans, floor plans, and roof layouts were largely complete.

That approach may create challenges under the new code.

Early coordination between developers, architects, MEP engineers, EPC contractors, and energy code consultants can help identify:

  • Available roof capacity
  • Structural considerations
  • Electrical infrastructure needs
  • Shading limitations
  • Long-term ownership and energy goals

The earlier those conversations happen, the more flexibility project teams have.

The later they happen, the more likely compliance solutions become redesign exercises.

Turning Energy Code Compliance into Opportunity

For many developers, architects, and engineers, the introduction of renewable energy requirements may initially feel like another box to check during permitting.

But the most forward-thinking project teams are viewing it differently.

The reality is that renewable energy is already influencing project economics by:

  • expanding project funding opportunities
  • reducing long-term operating costs
  • increasing energy resiliency
  • and even attracting sustainably minded stakeholders and building tenants

New York’s 2025 Energy Code simply brings conversations about renewable energy integration further upstream in the development process.

The teams that begin planning for it early will have more options, greater flexibility, and a better opportunity to align compliance requirements with overall project goals.

Planning a new commercial building project in New York?

GreenSpark works with developers, architects, engineers, and property owners to evaluate renewable energy requirements, identify practical compliance pathways, and develop solutions that align with project objectives.

More broadly, it reflects a larger trend toward integrating renewable energy and electrification considerations earlier in project planning. Teams that develop familiarity with solar-friendly design today will be better positioned to navigate future code requirements and market expectations.

Contact our team early in the design process to discuss how New York’s 2025 Energy Code may impact your next project.